Across 982 qualifying US industrial recommendations, the median projected simple payback was 0.9857 years. The middle half ran from 0.353 to 2.055 years. Those figures describe the assessed proposals for compressor sequencing controls, in fiscal years 1992 to 2026.

The scope of the plant change

Record input power and header pressure for every machine in the group. Look for overlapping unloaded operation as demand falls. Use the combined station kW at the same air delivery to calculate the prospective saving.

A recommendation you can reproduce

Recommendation WV053706 in US fiscal year 2017 pairs US$6,000 of implementation cost with US$6,093 in estimated annual net savings. Dividing the first figure by the second gives 0.9847 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$6,000 and the median annual saving was US$6,854. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for compressor sequencing controls. Lower quartile 0.353, median 0.9857 and upper quartile 2.055 years.
Estimated payback for compressor sequencing controls. Lower quartile 0.353, median 0.9857 and upper quartile 2.055 years. Figure by Industry Applied.

What the records can support

The source lists 1,074 recommendations under assessment code 2.4224. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 982 comparable records, 384 carry the implemented flag and 553 the non-implemented flag. The remaining 45 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UM032010

2007

1

4703

0.0002126302

OR039403

2001

4080

11580

0.3523316

WV053706

2017

6000

6093

0.9847366

TT030010

2023

17500

8509

2.056646

UD101105

2020

45000

2908

15.47455

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.313 years. At full forecast savings and a 20% higher installed cost, it would give 1.182 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.