Across 4,396 qualifying US industrial recommendations, the median projected simple payback was 0.08152 years. The middle half ran from 0.02312 to 0.4112 years. Those figures describe the assessed proposals for compressed-air pressure reduction, in fiscal years 1982 to 2026.
The scope of the plant change
Log the header and the pressure at the most demanding end use at the same time. A large difference under flow points to distribution restrictions. Include the highest-demand part of the shift before deciding what operating range can be sustained.
A recommendation you can reproduce
Recommendation AM097805 in US fiscal year 2025 pairs US$225 of implementation cost with US$2,760 in estimated annual net savings. Dividing the first figure by the second gives 0.08152 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$100 and the median annual saving was US$1,706. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 6,545 recommendations under assessment code 2.4231. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 4,396 comparable records, 2,094 carry the implemented flag and 2,075 the non-implemented flag. The remaining 227 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
IA029502 | 2002 | 20 | 143247 | 0.000139619 |
UD100501 | 2019 | 50 | 2162 | 0.02312673 |
AM097805 | 2025 | 225 | 2760 | 0.08152174 |
SD056405 | 2018 | 400 | 973 | 0.4110997 |
IC008207 | 2004 | 282150 | 311 | 907.2347 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 0.1087 years. At full forecast savings and a 20% higher installed cost, it would give 0.09783 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.