Across 10,525 qualifying US industrial recommendations, the median projected simple payback was 0.2469 years. The middle half ran from 0.1065 to 0.5651 years. Those figures describe the assessed proposals for compressed-air and inert-gas leak repairs, in fiscal years 1982 to 2026.

The scope of the plant change

Separate compressor input electricity from the volume of gas delivered. Record the quiet-shift demand, pressure at the header and compressors actually loaded. Where the gas is purchased, reconcile the volume balance to deliveries and opening and closing inventory.

A recommendation you can reproduce

Recommendation CO071202 in US fiscal year 2015 pairs US$1,000 of implementation cost with US$4,050 in estimated annual net savings. Dividing the first figure by the second gives 0.2469 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$620 and the median annual saving was US$2,750. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for compressed-air and inert-gas leak repairs. Lower quartile 0.1065, median 0.2469 and upper quartile 0.5651 years.
Estimated payback for compressed-air and inert-gas leak repairs. Lower quartile 0.1065, median 0.2469 and upper quartile 0.5651 years. Figure by Industry Applied.

What the records can support

The source lists 11,260 recommendations under assessment code 2.4236. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 10,525 comparable records, 7,686 carry the implemented flag and 2,234 the non-implemented flag. The remaining 605 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UF036102

2005

1

11264.13

8.877737e-05

MA029206

1994

100

939

0.1064963

CO071202

2015

1000

4050

0.2469136

UA015306

2016

2995

5300

0.5650943

SF031501

2005

312

2

156

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.3292 years. At full forecast savings and a 20% higher installed cost, it would give 0.2963 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.