Across 210 qualifying US industrial recommendations, the median projected simple payback was 1.463 years. The middle half ran from 0.6482 to 2.573 years. Those figures describe the assessed proposals for boiler blowdown heat recovery, in fiscal years 1983 to 2026.

The scope of the plant change

Compare the timing and energy content of blowdown with feedwater demand. Include scale management, inspection access and pump power. An annual heat total can overstate recoverable value if the two streams are available at different times.

A recommendation you can reproduce

Recommendation UU025603 in US fiscal year 2024 pairs US$11,730 of implementation cost with US$8,048 in estimated annual net savings. Dividing the first figure by the second gives 1.458 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$9,785 and the median annual saving was US$7,238. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for boiler blowdown heat recovery. Lower quartile 0.6482, median 1.463 and upper quartile 2.573 years.
Estimated payback for boiler blowdown heat recovery. Lower quartile 0.6482, median 1.463 and upper quartile 2.573 years. Figure by Industry Applied.

What the records can support

The source lists 212 recommendations under assessment code 2.1243. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 210 comparable records, 62 carry the implemented flag and 139 the non-implemented flag. The remaining 9 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IA035505

2004

3

9161

0.0003274752

OR064102

2014

8760

13580

0.6450663

UU025603

2024

11730

8048

1.457505

KU013409

1984

5000

1941

2.575992

SD001403

1992

1200

71

16.90141

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.943 years. At full forecast savings and a 20% higher installed cost, it would give 1.749 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.