Across 7 qualifying US industrial recommendations, the median projected simple payback was 0.3196 years. The middle half ran from 0.1419 to 0.7207 years. Those figures describe the assessed proposals for basing utility charges on usage rather than area occupied, in fiscal years 1985 to 2021.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation MZ031002 in US fiscal year 2021 pairs US$1,160 of implementation cost with US$3,630 in estimated annual net savings. Dividing the first figure by the second gives 0.3196 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$2,900 and the median annual saving was US$3,630. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for basing utility charges on usage rather than area occupied. Lower quartile 0.1419, median 0.3196 and upper quartile 0.7207 years.
Estimated payback for basing utility charges on usage rather than area occupied. Lower quartile 0.1419, median 0.3196 and upper quartile 0.7207 years. Figure by Industry Applied.

What the records can support

The source lists 7 recommendations under assessment code 2.8115. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 7 comparable records, 4 carry the implemented flag and 3 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 2000–2014, 3 qualifying records had a median of 0.9887 years. For fiscal years 2015–2026, 3 qualifying records had a median of 0.2111 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IC021201

2019

2920

59063

0.04943873

OK096602

2017

24000

113700

0.2110818

MZ031002

2021

1160

3630

0.3195592

MA002404

1985

2900

6406

0.4527006

AM047807

2005

18000

2130

8.450704

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.4261 years. At full forecast savings and a 20% higher installed cost, it would give 0.3835 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.