Across 500 qualifying US industrial recommendations, the median projected simple payback was 0.8686 years. The middle half ran from 0.3278 to 2.015 years. Those figures describe the assessed proposals for baling recovered cardboard, in fiscal years 1994 to 2026.

The scope of the plant change

Weigh loose and baled material over comparable collection intervals. Include bale storage, labour, lift-truck movements and any recycler specification for contamination. Check whether the avoided cost is per lift, per tonne or a fixed collection fee.

A recommendation you can reproduce

Recommendation MS010210 in US fiscal year 1998 pairs US$6,500 of implementation cost with US$7,480 in estimated annual net savings. Dividing the first figure by the second gives 0.869 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$6,000 and the median annual saving was US$4,506. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for baling recovered cardboard. Lower quartile 0.3278, median 0.8686 and upper quartile 2.015 years.
Estimated payback for baling recovered cardboard. Lower quartile 0.3278, median 0.8686 and upper quartile 2.015 years. Figure by Industry Applied.

What the records can support

The source lists 740 recommendations under assessment code 3.5315. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 500 comparable records, 183 carry the implemented flag and 282 the non-implemented flag. The remaining 35 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

BD022310

2003

100

36770

0.002719608

WV016612

1999

1260

3840

0.328125

MS010210

1998

6500

7480

0.868984

OD010804

1998

10000

4965

2.014099

SF031808

2005

10000

13

769.2308

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.159 years. At full forecast savings and a 20% higher installed cost, it would give 1.043 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.