Across 7 qualifying US industrial recommendations, the median projected simple payback was 0.1875 years. The middle half ran from 0.04226 to 0.7649 years. Those figures describe the assessed proposals for avoiding contamination of end pieces and reusing as feed stock, in fiscal years 1996 to 2013.

The scope of the plant change

Follow a measured quantity of material from receiving through saleable output to recovery or disposal. Account for moisture, rework and scrap sold separately. Capture both the unit price and the handling time so a reduced disposal bill is not counted twice.

A recommendation you can reproduce

Recommendation TN058207 in US fiscal year 1996 pairs US$1,500 of implementation cost with US$8,000 in estimated annual net savings. Dividing the first figure by the second gives 0.1875 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$5,464 and the median annual saving was US$18,000. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for avoiding contamination of end pieces and reusing as feed stock. Lower quartile 0.04226, median 0.1875 and upper quartile 0.7649 years.
Estimated payback for avoiding contamination of end pieces and reusing as feed stock. Lower quartile 0.04226, median 0.1875 and upper quartile 0.7649 years. Figure by Industry Applied.

What the records can support

The source lists 8 recommendations under assessment code 3.5215. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 7 comparable records, 3 carry the implemented flag and 4 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 4 qualifying records had a median of 0.1212 years. For fiscal years 2000–2014, 3 qualifying records had a median of 1.228 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

HO022514

2000

100

9938

0.01006239

TN064401

1998

20000

363750

0.05498282

TN058207

1996

1500

8000

0.1875

DS009306

1997

11176

37008

0.3019888

OR061107

2013

5464

1200

4.553333

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.25 years. At full forecast savings and a 20% higher installed cost, it would give 0.225 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.