Across 583 qualifying US industrial recommendations, the median projected simple payback was 0.9581 years. The middle half ran from 0.5246 to 1.652 years. Those figures describe the assessed proposals for automatic industrial demand control, in fiscal years 1981 to 2026.
The scope of the plant change
Map interruptible loads against the utility billing interval. Record process restart costs and any demand rebound after release. Replay the same monthly interval trace with and without the proposed control logic.
A recommendation you can reproduce
Recommendation GT033905 in US fiscal year 1988 pairs US$10,300 of implementation cost with US$10,750 in estimated annual net savings. Dividing the first figure by the second gives 0.9581 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$6,000 and the median annual saving was US$6,445. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 644 recommendations under assessment code 2.3191. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 583 comparable records, 225 carry the implemented flag and 333 the non-implemented flag. The remaining 25 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
UU007406 | 2004 | 12 | 3570 | 0.003361345 |
UU010401 | 2006 | 10000 | 19040 | 0.5252101 |
GT033905 | 1988 | 10300 | 10750 | 0.9581395 |
TN069204 | 2000 | 11900 | 7220 | 1.648199 |
OK039002 | 1992 | 8556 | 703 | 12.1707 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 1.278 years. At full forecast savings and a 20% higher installed cost, it would give 1.15 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.