Across 756 qualifying US industrial recommendations, the median projected simple payback was 0.3219 years. The middle half ran from 0.1109 to 0.8558 years. Those figures describe the assessed proposals for after-hours HVAC scheduling, in fiscal years 1981 to 2026.
The scope of the plant change
Trend occupancy, plant enable and plant demand through shutdown and restart. Account for the morning recovery peak and work that continues after the nominal end of shift. An enable signal on its own cannot reveal the power the plant used.
A recommendation you can reproduce
Recommendation UD094602 in US fiscal year 2016 pairs US$1,660 of implementation cost with US$5,148 in estimated annual net savings. Dividing the first figure by the second gives 0.3225 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$750 and the median annual saving was US$2,387. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 1,150 recommendations under assessment code 2.7224. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 756 comparable records, 336 carry the implemented flag and 362 the non-implemented flag. The remaining 58 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
TN049901 | 1993 | 49 | 40654 | 0.001205293 |
UM032013 | 2007 | 100 | 900 | 0.1111111 |
UD094602 | 2016 | 1660 | 5148 | 0.3224553 |
MA020404 | 1991 | 11160 | 13064 | 0.854256 |
UD105307 | 2023 | 110000 | 2097 | 52.45589 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 0.4299 years. At full forecast savings and a 20% higher installed cost, it would give 0.3869 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.