Across 183 qualifying US industrial recommendations, the median projected simple payback was 0.6737 years. The middle half ran from 0.2657 to 1.789 years. Those figures describe the assessed proposals for adding area lighting switches, in fiscal years 1993 to 2026.

The scope of the plant change

Record the circuit load, lighting hours and the actual visual task in the work area. Use separately controlled zones as measurement boundaries. Keep a record of daylight, shift occupancy and any maintenance intervention between the baseline and follow-up periods.

A recommendation you can reproduce

Recommendation AM037605 in US fiscal year 2000 pairs US$640 of implementation cost with US$950 in estimated annual net savings. Dividing the first figure by the second gives 0.6737 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,200 and the median annual saving was US$1,911. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for adding area lighting switches. Lower quartile 0.2657, median 0.6737 and upper quartile 1.789 years.
Estimated payback for adding area lighting switches. Lower quartile 0.2657, median 0.6737 and upper quartile 1.789 years. Figure by Industry Applied.

What the records can support

The source lists 194 recommendations under assessment code 2.7131. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 183 comparable records, 74 carry the implemented flag and 96 the non-implemented flag. The remaining 13 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 47 qualifying records had a median of 0.6116 years. For fiscal years 2000–2014, 105 qualifying records had a median of 0.6737 years. For fiscal years 2015–2026, 31 qualifying records had a median of 0.7832 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

DL006105

2010

120

23365

0.005135887

UD097614

2017

180

671

0.2682563

AM037605

2000

640

950

0.6736842

UF033104

2003

1649

924

1.784632

UF036207

2005

3655

357

10.2381

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.8982 years. At full forecast savings and a 20% higher installed cost, it would give 0.8084 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.