The recorded RLCLine_sc.terminal_n.phase[1].i[1] channel spans -17.713 to 6.016 A in this reference run. It starts at -17.713 and ends at 6. The first recorded maximum occurs at 0.01 seconds and the first minimum at 0 seconds.
The system being tested
Lawrence Berkeley National Laboratory publishes the Buildings test named ACLine_RLC. The source file places it under Electrical, AC, Three Phases Unbalanced, Lines. We used the 101 stored values for RLCLine_sc.terminal_n.phase[1].i[1] over the interval 0 to 1 seconds. This is a simulated test with specified inputs and boundaries.
The component declarations name E (Fixed Voltage), sc_load1 (Impedance), sc_load2 (Impedance), sc_load3 (Impedance). The source declares RBase = 3*10. These identifiers can be found in the linked model definition. Check how they connect to the plotted quantity before comparing it with a field meter or a differently named controller tag.
Compare the recorded channels
The companion channel RLCLine_sc.terminal_n.phase[1].i[2] covers -2.001 to 17.713 A. At 0 s, the primary value is -17.713 and the companion is 17.713. Their signed difference is -35.426 A, the largest absolute separation on the common grid. Check the two channels’ physical roles before interpreting that difference as any kind of error.
![Three-phase unbalanced rlc line. The simulated RLCLine_sc.terminal_n.phase[1].i[1] channel runs from -17.713 to 6.016 A over 1 seconds.](https://static.wixstatic.com/media/21e41b_0b4ad5d6f5c1446a9bf2a3873dbf161b~mv2.png/v1/fill/w_616,h_345,al_c,q_85,enc_auto/21e41b_0b4ad5d6f5c1446a9bf2a3873dbf161b~mv2.png)
Reproduce the calculation
The largest absolute change between consecutive stored points appears from 0 to 0.01 seconds. Subtracting -17.713 from 6.016 gives 23.729 A. Its location brackets the change within one saved interval of 0.01 seconds. It does not identify an unobserved instantaneous peak or the exact crossing time.
The worked table retains the first and last points, the primary maximum and minimum, the largest adjacent change and a spread of checkpoints across the run. Rounding is for presentation. Use the full linked reference series to repeat integrals or compare events between checkpoints. The archived sampling interval need not match the simulation solver’s internal step.
Worked data
Simulation time (s) | RLCLine_sc.terminal_n.phase[1].i[1] (A) | RLCLine_sc.terminal_n.phase[1].i[2] (A) |
|---|---|---|
0 | -17.71281 | 17.71281 |
0.01 | 6.01636 | -2.001049 |
0.2 | 6 | -2 |
0.4 | 6 | -2 |
0.6 | 6 | -2 |
0.8 | 6 | -2 |
1 | 6 | -2 |
What to check on site
Keep voltage, current, real power and energy distinct. Establish the reference direction at the measurement terminal before interpreting a sign change as import or export. Compare the same load boundary and duration in site data and the simulation.
State the operating duty, measurement location and expected tolerance before evaluating a local trend. Re-run the comparison with the installed controls and instruments during a representative operating period. Retain the native units and the raw export so that a later change in software or presentation can be investigated.
Data and source model
Published model and component definitions. Numerical reference series. Simulation and plot commands. Download the worked checkpoints in CSV format.
Cover photograph by Connor Scott McManus, via Pexels. The photograph illustrates the subject. Industry Applied produced the figure and calculations from the linked source.