The recorded ideUse.senMasFlo.m_flow channel spans 1.41e-06 to 1 kg/s in this reference run. It starts at 1.41e-06 and ends at 8.21e-06. The first recorded maximum occurs at 2,412 seconds and the first minimum at 0 seconds.
The system being tested
Lawrence Berkeley National Laboratory publishes the Buildings test named IdealUser. The source file places it under DHC, Plants, Cooling. We used the 101 stored values for ideUse.senMasFlo.m_flow over the interval 0 to 3,600 seconds. This is a simulated test with specified inputs and boundaries.
The component declarations name ideUse (Ideal User), sin (Boundary p T), sou (Boundary p T). The source declares m_flow_nominal = 1, dp_nominal = 500000, p_Pressurisation = 300000, QCooLoa_flow_nominal = 5*4200*0.9. These identifiers can be found in the linked model definition. Check how they connect to the plotted quantity before comparing it with a field meter or a differently named controller tag.
Compare the recorded channels
The companion channel mPre_flow.y starts at 0, ends at 0 and has a recorded range of 0 to 1 source units. Its time span matches the primary channel. Both are included to put the primary response in context. Their numerical scales may represent different physical quantities.

Reproduce the calculation
Integrating the signed rate over 3,600 seconds gives a net 857.456 kg. This estimate averages neighbouring stored rates and multiplies by their time separation. Reverse flow reduces the net total. If a process requires gross throughput, calculate forward and reverse transfers separately at the appropriate boundary.
The worked table retains the first and last points, the primary maximum and minimum, the largest adjacent change and a spread of checkpoints across the run. Rounding is for presentation. Use the full linked reference series to repeat integrals or compare events between checkpoints. The archived sampling interval need not match the simulation solver’s internal step.
Worked data
Simulation time (s) | ideUse.senMasFlo.m_flow (kg/s) | mPre_flow.y (source units) |
|---|---|---|
0 | 1.40625e-06 | 0 |
720 | 1.40625e-06 | 0 |
1440 | 1.40625e-06 | 0 |
2160 | 0.9999568 | 1 |
2412 | 1 | 1 |
2700 | 0.9999999 | 1 |
2736 | 0.4178217 | 0 |
2880 | 0.0225769 | 0 |
3600 | 8.21203e-06 | 0 |
What to check on site
Trace the transfer boundary between the central network and the local load. Identical terminal duty can coincide with different distribution losses and pump inputs. Use simultaneous primary and secondary measurements before allocating an energy difference to one side.
State the operating duty, measurement location and expected tolerance before evaluating a local trend. Re-run the comparison with the installed controls and instruments during a representative operating period. Retain the native units and the raw export so that a later change in software or presentation can be investigated.
Data and source model
Published model and component definitions. Numerical reference series. Simulation and plot commands. Download the worked checkpoints in CSV format.