For irrigation scheduling, the working limit is the water available to the crop’s active roots before the chosen stress threshold is reached. Readily available water depends on both the soil and the effective rooting depth. Two nearby blocks can have the same moisture reading at 20 cm and very different amounts of water left before their next irrigation.
Build the root zone a layer at a time
Take a hypothetical Victorian irrigation block with roots active to 0.50 m. In the first 0.20 m, the difference between volumetric water content at field capacity and at permanent wilting point is assumed to be 0.16 m³/m³. This layer holds 0.20 × 0.16 × 1,000 = 32 mm of total available water. In the next 0.30 m, the assumed difference is 0.10 m³/m³, giving another 30 mm. The combined total available water is 62 mm. A shallow soil pit, restricted root growth or a different texture in the second layer could change that result substantially.
Use an illustrative allowable depletion fraction of 0.45. The readily available amount is then 62 × 0.45 = 27.9 mm from field capacity. This is a depletion threshold, not a target irrigation depth for every event. FAO Irrigation and Drainage Paper 56 explains how the depletion fraction varies with crop and evaporative demand. A grower needs a local basis for choosing it. Where a local soil table already gives readily available water directly for a chosen tension range, applying a second depletion fraction to that value would count the adjustment twice.
Turn millimetres into a scheduling decision
Suppose today’s estimated depletion is 18 mm. Forecast crop water use is 5 mm per day for three days. The first day delivers an assumed 3 mm of effective rain and the next two days are dry. With no irrigation, end-of-day depletion becomes 20 mm, 25 mm and 30 mm. The available margin after day two is only 2.9 mm. On these assumptions the threshold is crossed during the third day, so a system that takes a day to cover the block needs to start earlier than a system that can deliver water immediately.

A rain gauge may record more than the water retained in the active root zone. Canopy interception, runoff or drainage change the effective amount. If the forecast 3 mm never reaches the root zone, the same calculation gives 23, 28 and 33 mm. The planned start moves forward by nearly a day. This sensitivity is worth discussing before choosing the start time simply from the rainfall total in a phone app.
Check the block after the event
Inspect the root depth and soil layers in representative locations. A compacted strip, shallow ridge or poorly wetted edge can behave differently from the probe location.
Compare water content at more than one depth before and after irrigation. An immediate rise near the surface with little response lower down is a clue to check the wetting pattern and the time allowed for infiltration.
Record the applied depth, measured application rate, rainfall and crop stage. If several blocks share a pump, include the time required to complete the rotation before the driest block reaches its refill point.
Reconcile the next observation with the forecast depletion. A repeated mismatch warrants checking the root depth, available water estimate, local rainfall or crop water use rather than copying last week’s start interval.
The result is a scheduling window with assumptions a farm manager can check in the paddock. If the active root zone is shallower than the example, the reserve shrinks. If effective rainfall is greater than assumed, the window can move out. Recalculate whenever a root inspection, irrigation measurement or weather observation changes one of those inputs.
Sources and working data
Agriculture Victoria’s irrigation scheduling guidance connects readily available water, crop demand and application rate. FAO 56, Chapter 8 defines total and readily available water. Download the worked root-zone balance. The farm purchasing directory lists local irrigation and equipment enquiry routes.