Manufacturing
Measure changeover from the last good pack to the next
A line can restart several minutes before it produces saleable output. Time the complete changeover and separate work that can be prepared in advance.

A carton line is reported as ready the moment the drive starts. The quality team releases the first acceptable pack nine minutes later. Which time counts depends on the question. For planning a production schedule, the more useful interval runs from the last good pack of one product to the first good pack of the next.
Agree on the two observations
Ask the operator and quality lead to mark the last accepted unit, last motion, restart and first accepted unit on the same clock. Record which changeover family is involved. A label roll swap and a full pack-format change do not present the same work. Observe one change before changing the procedure.
For example, the last accepted carton leaves at 10:02, the line restarts at 10:19 and the first approved new carton leaves at 10:28. The complete gap is 26 minutes. Seventeen minutes elapsed before restart and a further nine before acceptance.

What to check on site
Separate preparation that can be completed while the preceding run is still producing.
Record waiting for parts, setup verification and quality-release time separately.
Repeat the observation for the same pack change, checking that startup waste remains acceptable.
A trans-Tasman packer can use the same event definitions at both plants while keeping their procedures and release authority local. The paired timestamps make disagreements about the reported time easy to resolve.
Sources and photograph
Lean Enterprise Institute — quick changeover
A carton line is reported as ready the moment the drive starts. The quality team releases the first acceptable pack nine minutes later. Which time counts depends on the question. For planning a production schedule, the more useful interval runs from the last good pack of one product to the first good pack of the next.
Agree on the two observations
Ask the operator and quality lead to mark the last accepted unit, last motion, restart and first accepted unit on the same clock. Record which changeover family is involved. A label roll swap and a full pack-format change do not present the same work. Observe one change before changing the procedure.
For example, the last accepted carton leaves at 10:02, the line restarts at 10:19 and the first approved new carton leaves at 10:28. The complete gap is 26 minutes. Seventeen minutes elapsed before restart and a further nine before acceptance.

What to check on site
Separate preparation that can be completed while the preceding run is still producing.
Record waiting for parts, setup verification and quality-release time separately.
Repeat the observation for the same pack change, checking that startup waste remains acceptable.
A trans-Tasman packer can use the same event definitions at both plants while keeping their procedures and release authority local. The paired timestamps make disagreements about the reported time easy to resolve.
Sources and photograph
Lean Enterprise Institute — quick changeover