Technology Outlook · Manufacturing
Will the waste heat be there when the wash line needs it?
Overlay a plant’s heat source and hot-water demand before sizing an industrial heat pump. A four-hour example exposes the timing mismatch.

Hot-water demand is obvious during washdown. The warm effluent or refrigeration rejection that could supply a heat pump may peak much earlier. Before a New Zealand or Australian processor commissions detailed design, two synchronised load profiles can reveal whether direct recovery is likely to work.
Plot both loads on the same clock
Start with the source temperature, available thermal duty and timing. Record the required sink temperature, duty and operating hours independently. Ask the designer for the usable delivered heat at those temperatures, including compressor input and practical operating limits. Compare delivered capacity with sink demand in matching intervals.
Consider four one-hour periods. A proposed unit could deliver 80, 80, 20 and 0 kW of heat. Demand is 10, 50, 70 and 60 kW. With no storage or supplementary heating, the matched amounts are 10, 50, 20 and 0 kWh. Only 80 of the 190 kWh demanded coincides with available delivery.

What to check on site
Include low-load, shutdown and washdown periods in the survey.
Check the return temperature as well as the requested hot-water supply temperature.
Price storage and backup against the unmatched intervals, allowing for losses.
EECA’s integration guidance is useful at the next stage. A supplier’s maximum outlet temperature answers one question. The measured coincidence and temperature lift determine which operating hours belong in the business case.
Sources and photograph
EECA — integrating industrial high-temperature heat pumps
Hot-water demand is obvious during washdown. The warm effluent or refrigeration rejection that could supply a heat pump may peak much earlier. Before a New Zealand or Australian processor commissions detailed design, two synchronised load profiles can reveal whether direct recovery is likely to work.
Plot both loads on the same clock
Start with the source temperature, available thermal duty and timing. Record the required sink temperature, duty and operating hours independently. Ask the designer for the usable delivered heat at those temperatures, including compressor input and practical operating limits. Compare delivered capacity with sink demand in matching intervals.
Consider four one-hour periods. A proposed unit could deliver 80, 80, 20 and 0 kW of heat. Demand is 10, 50, 70 and 60 kW. With no storage or supplementary heating, the matched amounts are 10, 50, 20 and 0 kWh. Only 80 of the 190 kWh demanded coincides with available delivery.

What to check on site
Include low-load, shutdown and washdown periods in the survey.
Check the return temperature as well as the requested hot-water supply temperature.
Price storage and backup against the unmatched intervals, allowing for losses.
EECA’s integration guidance is useful at the next stage. A supplier’s maximum outlet temperature answers one question. The measured coincidence and temperature lift determine which operating hours belong in the business case.
Sources and photograph
EECA — integrating industrial high-temperature heat pumps