How much rooftop solar does the factory actually use?
Two solar percentages answer different questions. Work from generation, exports and imported electricity over the same interval.

A workshop reports that it uses most of its rooftop solar, while the accounts team still sees substantial electricity imports. Those statements can both be true. The fraction of solar generation used on site and the fraction of site demand supplied by solar have different denominators.
Reconcile the three energy streams
For a simple site with one grid connection, no battery and no other generator, take inverter generation, meter exports and meter imports over identical intervals. On-site solar use equals generation minus exports. Add imports to that on-site use to calculate the electricity consumed behind the meter.
A worked shift generates 120 kWh, exports 30 kWh and imports 90 kWh. The factory consumed 90 kWh of solar and 180 kWh in total. Self-consumption is 90 ÷ 120 = 75%. Solar supplied 90 ÷ 180 = 50% of site consumption.

What to check on site
Check import and export register directions on the meter export.
Confirm that all inverters and the same buildings fall inside the reporting boundary.
Keep battery charging, discharging and losses explicit if storage is installed.
A processor considering a daytime changeover can repeat the calculation with interval data from comparable days. Check whether moving the load altered exports, imports or both before assigning a dollar benefit.
Sources and photograph
Australian Government — using solar generation on site
A workshop reports that it uses most of its rooftop solar, while the accounts team still sees substantial electricity imports. Those statements can both be true. The fraction of solar generation used on site and the fraction of site demand supplied by solar have different denominators.
Reconcile the three energy streams
For a simple site with one grid connection, no battery and no other generator, take inverter generation, meter exports and meter imports over identical intervals. On-site solar use equals generation minus exports. Add imports to that on-site use to calculate the electricity consumed behind the meter.
A worked shift generates 120 kWh, exports 30 kWh and imports 90 kWh. The factory consumed 90 kWh of solar and 180 kWh in total. Self-consumption is 90 ÷ 120 = 75%. Solar supplied 90 ÷ 180 = 50% of site consumption.

What to check on site
Check import and export register directions on the meter export.
Confirm that all inverters and the same buildings fall inside the reporting boundary.
Keep battery charging, discharging and losses explicit if storage is installed.
A processor considering a daytime changeover can repeat the calculation with interval data from comparable days. Check whether moving the load altered exports, imports or both before assigning a dollar benefit.